The board approved street improvement cost-sharing with Wheatland Township, a mutual aid IGA with Na-Au-Say Township, and engineering contract amendments for West Electric Park.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 19, 2026.
Impact analysis
Strand Associates engineering amendment increases project cost to a not-to-exceed total of $68,100.00.
Plainfield residents and neighboring township taxpayers benefit from cooperative public works and upgraded park facilities.
Mentions & discussions (2)
Meeting of the President and the Board of Trustees - Oct 19, 2026
The village is acquiring 2.91 acres of land at Van Dyke Road and Village Center Drive from Marquette Land Advisors to permanently add to Settlers Park. In exchange, the village will waive up to $1.8 million in building permit fees for the Cornerstone development.
Meeting of the President and the Board of Trustees - Feb 2, 2026
The board approved street improvement cost-sharing with Wheatland Township, a mutual aid IGA with Na-Au-Say Township, and engineering contract amendments for West Electric Park.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Plainfield
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.